This was announced Friday at a press conference.
“We are confident that this date is actually achieved,” said Alderman Pieter Litjens. “This is a realistic date.” He called the completion of the North-South line once before an Olympic challenge and emphasized those words Friday yet again.
The delay be caused by problems during the construction of the line and by contractors bankruptcies that were responsible for the building.
When the final construction decision was made was based in 2002 Completion in March 2011. the budget was 1.4 billion euros, but in the meantime there is already 3.1 billion spent on the project
Video:. Again delay completion North-South
Cost
Litjens declares that the delay also additional costs associated, but they fit within the budget of 3.1 billion euros available for the project.
in 2009, it was estimated would ride the new metro in Amsterdam in October 2017. Thursday all came out that the opening of the North-South line would probably be in the summer of 2018
It is expected that the project is fully completed in late June 2018. The start date of July 22 was chosen because on that day also enters the summer schedule. ” This allows us to the risks of unforeseen startup problems for travelers minimize. “
Litjens said at the beginning of the press conference that Wednesday, July 13 will be a hearing in the City of Amsterdam which experts the word out about the new target date